top of page

Managing Complexity Across Borders: The Hotel Renovation in Bruges, Belgium

Updated: May 8



On paper, managing the renovation of a hotel was straightforward.


In reality, it also meant coordinating multiple countries, strict regulations, and parallel teams, renovating a hotel of 24 rooms within roughly three months.


With the client based in Australia, a key requirement from the start was having a trusted on site representative to act as the interface between construction, design, and execution.

Archiformus supported the project through on site project management and client representation, ensuring coordination between all stakeholders throughout the renovation process.


This role became essential in ensuring that decisions made remotely could be translated accurately on site without delay or distortion.


When the hotel set out to transform from a 3-star property into a 4-star boutique hotel, the project involved not only the planned upgrade, but also addressing a significant renovation backlog across the property.


The FF&E works and design were commissioned to The Fitouter, a Berlin based company responsible for the project’s interior concept and FF&E scope.


With design and FF&E coordination distributed across different stakeholders, on site execution also had to operate within Belgium’s strict construction and labor framework. Before works could properly begin, builder registration and compliance procedures had to be completed, adding a necessary operational layer that extended beyond a standard renovation process.


From the outset, we ensured coordination on site so that remote decisions could be translated into real execution without disconnect or delay.


Understanding the Existing Condition


Images of two rooms and a bathroom before renovation


Following a pre assessment, a soft renovation approach was confirmed, focusing on the renewal of surface materials and furniture rather than any structural refurbishment.


However, some underlying technical issues were identified that required careful assessment before finishing works could proceed.


Some bathrooms required only cosmetic updates. Others required partial upgrades. In several areas, moisture related risks and plumbing checks had to be addressed before work could continue safely and correctly.


Key works included:

  • Bathroom updates ranging from cosmetic fixes to partial refurbishment

  • Drywall adjustments due to previous built in structures

  • Subfloor corrections in selected rooms

  • Moisture and plumbing checks in identified areas



From left to right: Water damage in rooms; partial damage to subfloors; dry wall installation required


The Execution Phase


Once works started, we saw progress move across multiple trades simultaneously.


Flooring, drywall, and painting works advanced across rooms and corridors. As these were completed, FF&E items were delivered, installed, and fixed in place according to specification.


At the same time, technical systems including HVAC and electrical infrastructure were brought into operation.


The main challenge was maintaining alignment across multiple teams working in parallel under a compressed delivery schedule.


Work in progress: Installation and painting works across floors


Final Phase


As completion approached, we shifted focus from progress to precision.


Room by room checks highlighted remaining items such as:


  • Minor finishing works (silicone, skirting, fittings)

  • Installation of lamps, mirrors, and remaining FF&E elements

  • Coordination with external vendors for TVs and fire safety systems

  • Final testing of HVAC, electrical, and room systems


At this stage, even small inconsistencies become critical, and coordination becomes essential to ensure nothing is left unresolved across the building.


Completion


The hotel transitioned from a stripped interior to a fully functional space within a tightly managed timeframe.


FF&E installation was completed, systems were tested, and rooms were brought to operational readiness, with only minor final adjustments remaining at handover.


Final delivered guest room and bathroom after renovation


Role of Coordination


Design responsibility remained with the commissioned team in Berlin. There was only a short gap between commission and site commencement, with design completed approximately three weeks prior to construction start. This resulted in design and construction progressing almost in parallel.


On site, our role included:


  • Supporting contract negotiations

  • Defining the overall project scope with the contractor

  • Assisting in design approvals to ensure alignment between intent and execution


With the client based remotely, coordination became the stabilizing layer, ensuring decisions were accurately translated into execution on site.


Final Reflection


Projects like this are not defined by construction alone. They are defined by how effectively design, execution, and decision making are aligned under constrained timelines and distributed responsibilities.


A full hotel renovation in Bruges, Belgium was delivered within a tightly compressed program, despite strict regulatory requirements and fast moving site conditions.


In such environments, success depends on maintaining continuous alignment between all stakeholders so that design intent is accurately translated into execution on site.

Ultimately, this highlights the importance of structured project management and clear client representation in ensuring that decisions are coordinated effectively and delivery remains aligned with project objectives.

 
 
 

Comments


Telefon

Büroadresse

Nachodstr. 18 

10779 Berlin  

E-mail

© 2025 by archiformus Germany

bottom of page